WIS 23 Expansion - Sheboygan/FDL

Sheboygan/Fond du Lac Counties

Schedule

Construction Impacts

For weekly construction updates and traffic impacts, please click on the link below. Projects are listed by county, so look under Fond du Lac County and Sheboygan County for WIS 23 Projects.

Fond du Lac County – US 151 to Seven Hills Road

Description of work:  This portion of the WIS 23 improvement project will reconstruct and raise the profile of the existing four lane portion of WIS 23 from US 151 to Whispering Springs Boulevard and expand WIS 23 from 2 lanes to 4 lanes from Whispering Springs Boulevard to Seven Hills Road.  Interchanges will be constructed at County K and County UU, intersection improvements will also be made throughout the corridor.

Traffic impacts: Please use alternate routes to access these locations. Several new local roads were constructed in 2021 and open to traffic that allow access to residents and businesses.

    • County K
      • Closed north of WIS 23
      • No left turns from south County K
    • Whispering Springs Drive
      • No left turn from Whispering Springs to EB WIS 23
      • No left turn from EB WIS 23 to Whispering Springs
    • County UU
      • County UU closed north and south of WIS 23
    • Hilltop Drive
      • Connection to WIS 23 will close permanently in late spring 2022
    • Taft and Tower and Poplar roads
      • Close for 14 days each to construct new intersections in late summer 2022
    •  US 151 ramps
      • Southbound US 151 ramp to close for 10 days in fall 2022. A detour will be posted
      • Northbound US 151 ramp widening construction will cause ramp delays in summer of 2022

Fond du Lac and Sheboygan County – Seven Hills Road to County P (Begins May 9, 2022)

Description of work: This portion of the WIS 23 improvement project will resurface (Mill and overlay) the original WIS 23 lanes, includes rumble strips and pavement markings. This is the last project of the WIS 23 Expansion Majors project.

Traffic impacts: Long term lane closures.