Schedule
April 1, 2024 – Tree clearing ends
May 2024 – Roadwork begins
October 31, 2024 – Anticipated completion
Traffic impacts
The road will be closed and detoured (local traffic only; no thru traffic) to occur no earlier than May 28 and be opened by September 13. The posted state highway detour route will use WIS 56 and US 14. For the balance of the project, the road will remain open to traffic under flagging operations.