WIS 69 (Bushnell Creek to Cow Path Lane)

Monroe to New Glarus, Green County

Schedule

Pre-construction meeting: May 21, 2026

Construction begins: May 26, 2026

Anticipated completion: November 1, 2026

 

Traffic impacts

WIS 69 will be closed and detoured to through traffic during culvert replacement

WIS 69 will remain open to traffic under flagging operations

 

Weekly update

Work operations and dates listed below are always subject to change due to weather and other unforeseen situations that arise.

Road Closures:

  • STH 69 and CTH C/Urban Rd are open to traffic as of Friday August 28th.

STH 69 Work Operations (south of Wittenwyler Rd)

  • Milling and paving from Monroe to Monticello is anticipated to begin Monday October 19th .   This work is weather dependent and subject to adjustments.

STH 69 Work Operations (north of Monticello)

  • No work is anticipated next week between Monticello and New Glarus.   

CTH C, Wittenwyler Rd Reconstruction Area Work Operations

  • Wittenwyler Rd to CTH F opened to traffic Friday August 28th , along with the rest of STH 69.

PLAN AHEAD: TWO WEEK LOOK-AHEAD FOR week of October 26  

  • Milling and Paving will continue between Monroe and Monticello.   This work will be done utilizing a flagging operation.  This work is anticipated to finish early this week.  Remaining work to follow will be Aggregate Shoulders, Guardrail, pavement markings, and rumble strips.  Delays can be anticipated throughout the working day for all of these operations.   This work is weather dependent and subject to adjustments.