Schedule
Pre-construction meeting: May 21, 2026
Construction begins: May 26, 2026
Anticipated completion: November 1, 2026
Traffic impacts
WIS 69 will be closed and detoured to through traffic during culvert replacement
WIS 69 will remain open to traffic under flagging operations
Weekly update
Work operations and dates listed below are always subject to change due to weather and other unforeseen situations that arise.
Road Closures:
- STH 69 and CTH C/Urban Rd are open to traffic as of Friday August 28th.
STH 69 Work Operations (south of Wittenwyler Rd)
- Milling and paving from Monroe to Monticello is anticipated to begin during the week of October 12th. Minor work operations next week may take place in this stretch of the project. This work is weather dependent and subject to adjustments.
STH 69 Work Operations (north of Monticello)
- Guardrail and Pavement marking placement next week between Monticello and New Glarus. This work will be done utilizing a flagging operation. Delays can be anticipated throughout the working day. These work operations are weather dependent and subject to adjustments.
CTH C, Wittenwyler Rd Reconstruction Area Work Operations
- Wittenwyler Rd to CTH F opened to traffic Friday August 28th , along with the rest of STH 69.
PLAN AHEAD: TWO WEEK LOOK-AHEAD FOR week of October 12
- Milling and Paving will begin between Monroe and Monticello. This work will be done utilizing a flagging operation. This work is anticipated to take 8-9 days over the next 2 weeks. Delays can be anticipated throughout the working day. This work is weather dependent and subject to adjustments.