WIS 33 (Mulberry Street to County T)

Baraboo, Sauk County

Schedule

Check out the weekly update

February 19, 2024 – Pre-construction Public Meeting

Stage 2A: February 26, 2024 to May 30, 2024

West project limits: 200 ft West of Mulberry St intersection – 500 ft East of Village and city limits

200 ft West of Oak St Intersection – Barker St Intersection

West of Jefferson St (between the driveways of Spinning Wheel Motel) – Lincoln Ave Intersection

Stage 2B: May 31, 2024 to August 14, 2024

500 ft East of Village and City limits – 100 ft East of Park St Intersection

Barker St Intersection – West of Jefferson St Intersection

Stage 3A: August 15, 2024 to November 15, 2024

100 ft East of Park St Intersection – 200 ft West of Oak St Intersection

 

Traffic impacts

WIS 33 will be closed and detour utilizing I-90/94 and US 12.