Schedule and Traffic Impact
Page last updated: June 5, 2026
Schedule: April 9 to July 31, 2026
Anticipated work scheduled: Crews will:
- Begin concrete repair and replacement work in the westbound lanes from County Road D to County Road OO
- Begin approach work, surface drains and guardrail installation on the east of project near South Embarrass River Bridge
Traffic impacts (the next 10 days):
- Traffic on WIS 29 will be shifted to bi-directional travel on the westbound lanes between County D and County OO, with one lane open in each direction and speeds reduced to 55 mph.
- Eastbound travel will be restricted to 14 feet wide lane.
- Starting Tuesday, June 9, traffic will be transitioned to bi-directional travel on the eastbound lanes between County Road D and County Road OO, with one lane open in each direction and speeds reduced to 55 mph.
- Westbound travel will be restricted to 14 feet.