WIS 29, County D to County OO

 Marathon and Shawano County

Schedule and Traffic Impact

Page last updated: June 12, 2026

Schedule: April 9 to July 31, 2026

Anticipated work scheduled: Crews will:

  • Begin concrete repair and replacement work in the westbound lanes from County Road D to County Road OO
  • Begin approach work, surface drains and guardrail installation on the east of project near South Embarrass River Bridge

Traffic impacts (the next 10 days): 

  • Traffic will be transitioned to bi-directional travel on the eastbound lanes between County Road D and County Road OO, with one lane open in each direction and speeds reduced to 55 mph.
  • Eastbound travel will be restricted to 14 feet.