WIS 29, County D to County OO

 Marathon and Shawano County

Schedule and Traffic Impact

Page last updated: May 1, 2026

Schedule: April 9 to July 31, 2026

Anticipated work scheduled: Crews will:

  • Continue removing existing concrete pavement and grading for new concrete placement in the eastbound lanes
  • Perform concrete pavement joint removals and replacements throughout the eastbound lanes
  • Continue repair work on the bridge over the South Embarrass River

Traffic impacts (the next 10 days): 

  • Traffic on WIS 29 will be shifted to bi-directional travel on the westbound lanes between County D and County OO, with one lane open in each direction and speeds reduced to 55 mph.
  • Eastbound travel will be restricted to 14 feet wide lane.