Schedule and Traffic Impact
Page last updated: May 22, 2026
Schedule: April 9 to July 31, 2026
Anticipated work scheduled: Crews will:
- Pave eastbound shoulders and intersections
Traffic impacts (the next 10 days):
- Traffic on WIS 29 will be shifted to bi-directional travel on the westbound lanes between County D and County OO, with one lane open in each direction and speeds reduced to 55 mph.
- Eastbound travel will be restricted to 14 feet wide lane.