County B North of I-94 Projects
The Dunn County Highway Department has a separate pavement improvement project on County B north of I-94 from Badger Drive to 650th Avenue. In addition, Union Pacific will be completing improvements to the rail crossing just north of Badger Drive.
- Project scope: The existing pavement will be pulverized, and new pavement will be placed. The project also includes curb, gutter, storm sewer and streetlight work.
- Schedule: Construction tentatively is set to start April 15 and take seven to eight months to complete.
- Traffic impacts: County B will be closed for the duration of the work, and traffic will be detoured via WIS 40 and US 12/WIS 29.
- Information: Dunn County Highway Department: (715) 232-2181 or hwy@co.dunn.wi.us.