County B, US 12/WIS 29 to Eastbound I-94 Ramps

Dunn County 

Traffic Impacts

During the reconstruction project, County B will remain open to through traffic south of I-94, with work completed in stages and the following impacts:

Stage 1 (Anticipated April 1 to May 31)

  • Constructing temporary crossovers, widening and installing temporary traffic signals.
  • Traffic will be maintained on existing lanes, but motorists will encounter lane closures.

Stage 2 (Anticipated June 1 to Aug. 2)

  • Reconstructing the northbound lanes on County B.
  • Using crossovers, traffic will be maintained on southbound County B, with one lane of traffic in each direction.

Stage 3 (Anticipated Aug. 3 to Oct. 2)

  • Reconstructing the southbound lanes on County B.
  • Using crossovers, traffic will be maintained on northbound County B, with one lane of traffic in each direction.

Stage 4 (Anticipated Oct. 3 to Nov. 1)

  • Removing temporary crossovers and pavements and completing any finishing work.