WIS 59 Resurfacing (Waukesha to Eagle)

Waukesha County

Project Details

This WisDOT project will resurface and make various improvements to approximately 12.6 miles of WIS 59 (Genesee Road/State Road), between County X (Saylesville Road) and WIS 67, in Waukesha County.

Improvements:

  • Mill and overlay (resurface) WIS 59 within project limits
  • Replace traffic signal at County E in the village of North Prairie
  • Extend right turn lanes at Eagle Drive, Oak Ridge Drive, Piper Road, and Corby Drive
  • Replace railroad crossing surface and upgrade warning devices at the crossing west of North Prairie
  • Resurface bridge structures over Genesee Creek
  • Resurface bridge structure over Saylesville Creek
  • Upgrade curb ramps in the villages of Eagle and North Prairie
  • Replace sections of guardrail
  • Add rumble strips along the centerline and shoulders along WIS 59
  • New pavement markings

Traffic Impacts and Detours:

WIS 59 is scheduled to be closed to through traffic during construction. Detours will be utilized for this project.

View Detour Map

  • A long-term detour will be posted utilizing WIS 59 to WIS 67 to US 18 to WIS 59.
  • A short-term detour within the work zone will be posted utilizing Road X and County E for the reconstruction of the Wisconsin & Southern Railroad Crossing.
  • Access to local residences and businesses will be maintained

Motorists are always encouraged to check 511wi.gov for the latest information on traffic conditions before any drive.

Schedule:

Construction is scheduled to begin in mid-March 2026 and be completed by late fall 2026. All work is weather dependent and subject to change.

Business Resources:

Own a business along WIS 59? View WisDOT’s In This Together guide for tips, tools, and resources for local businesses to plan for highway construction.