US 45 Reconstruction (Rawson Ave. to College Ave.)

Milwaukee County

Project Details

This project will reconstruct US 45 from Rawson Avenue to College Avenue in Franklin, addressing the deteriorating pavement conditions and improving traffic operations.

Project Improvements:

  • Reconstruct existing roadway
  • New pedestrian sidewalks and shoulder for bike accommodations
  • Replace the traffic signal at Speedway Drive
  • Replace the storm sewer system
  • New detention pond
  • New pavement marking and signing

Traffic Impacts

Work will be completed in stages with US 45 remaining open to traffic during construction. See the updates page for latest project information.

  • Stage 1 consisting of preconstruction work was completed in 2023.
  • Stage 2 will move all traffic to the northbound lanes while the southbound lanes are reconstructed in spring/summer.
  • Stage 3 will move all traffic to the southbound lanes while the northbound lanes are reconstructed in summer/fall.

Side streets may close at different times throughout this process. Access to local residences and businesses will be maintained.