US 45 Reconstruction (Rawson Ave. to College Ave.)

Milwaukee County

Updates

May 31 Update

Stage 2 road construction work is ongoing on US 45 (Lovers Lane) from Rawson Avenue to College Avenue in Franklin. All traffic has been moved to the northbound lanes while the southbound lanes are reconstructed in spring/summer. US 45 will remain open to traffic throughout construction.

Traffic Updates – Week of 05/27/2024 – 6/03/2024:

  • Friday 5/31/2024: There will be alternating closures at W Cortez Road and Prairiewood Lane throughout the day tomorrow. One of these roads will always remain open. By the end of the day tomorrow, both roads should be reopened.
  • Monday 6/03/2024: Construction on the west leg of Speedway Drive will start on Monday. Traffic will be shifted down to two-lanes, maintaining one-way traffic in each direction throughout construction. All lanes are expected to be fully open by Friday morning, June 7th.

Sign up for project updates: Request to be added to the project’s distribution list by emailing Leah.Redding@graef-usa.com