Skip to content
June 5, Long-term Closure of I-43 Ramps at Green Bay Avenue
March 1, 2023 - Northbound Traffic Switch
December 15, 2022 - I-43 Northbound Reopens to Three Lanes Over Winter Months
December 3, 2022 - I-43 Southbound Traffic Switch
October 27, 2022 - Daytime and Overnight Bridge Work to Begin
June 30, 2022 - Southbound Traffic Switch
May 12, 2022 - Southbound Bridge Demo at Hampton/Milwaukee River
April 29, 2022 - Southbound Traffic Switch
April 1, 2022 - Overnight Bridge Demo at Green Bay Ave Exit Ramp
March 4, 2022 - Long Term Lane Closures
December 2021 - Work Completed and Winter Shutdown
June 2021 - Project Start and Overview