WIS 97, Black Creek Bridge

Marathon County

Schedule and Traffic Impacts

Page last updated: June 5 2026

Schedule: March 30 to July 2026

Anticipated work scheduled: Crews will:

  • Form and pour the paving notch additions to the north and south abutments
  • Work on structure overcoating cleaning and priming at the piers
  • Work on replacing concrete sidewalk, curb and gutter, and approach slabs

Traffic impacts (the next 10 days): 

  • During construction, WIS 97 will be closed and detoured via County A, WIS 13 and WIS 64.