Schedule and Traffic Impacts
Page last updated: June 19 2026
Schedule: March 30 to July 2026
Anticipated work scheduled: Crews will:
- Finish removal of the existing bridge deck polymer overlay
- Apply the new bride deck polymer overlay
- Install guardrail
- Complete remaining restoration work
- Apply pavement markings
Traffic impacts (the next 10 days):
- During construction, WIS 97 will be closed and detoured via County A, WIS 13 and WIS 64.