Business Updates
Businesses remain open along WIS 87 in St. Croix Falls.
No work is occurring on the project today (Friday, Oct. 9).
For the week of Oct. 12:
- The crews plan to begin switching traffic and pedestrian controls to stage B on the east side of WIS 87 from East State Street to East Massachusetts Steet on Monday, Oct. 12.
- The contractor plans to begin removals on Tuesday, Oct. 13, and electrical work on Thursday, Oct. 15. Crews also will be prepping for new concrete as the existing concrete is removed.
- Parking on the east side of WIS 87 may be affected during this work.
Schedules are contractor and weather dependent and subject to change.