Schedule and Traffic Impacts
Page last updated: July 24, 2026
Schedule: June 3 to Sept. 9, 2026
Anticipated work scheduled: Crews will:
- Continue replacing curb and gutter
- Continue culvert replacements near Iron Belt
Traffic impacts (the next 10 days):
- Motorists will encounter shoulder closures and flagging conditions.
- 10-foot maximum width through various areas will begin.
- Sideroads will be closed for ramp construction including but not limited to:
- Stratford Road
- Laurence Street north
- Hamilton Street south
- Buckeye Street