WIS 77, Upson Lake Road to Odanah Road

 Iron County

Schedule and Traffic Impacts

Page last updated: July 24, 2026

Schedule: June 3 to Sept. 9, 2026

Anticipated work scheduled: Crews will:

  • Continue replacing curb and gutter
  • Continue culvert replacements near Iron Belt

Traffic impacts (the next 10 days): 

  • Motorists will encounter shoulder closures and flagging conditions.
    • 10-foot maximum width through various areas will begin.
  • Sideroads will be closed for ramp construction including but not limited to:
    • Stratford Road
    • Laurence Street north
    • Hamilton Street south
    • Buckeye Street