Schedule and Traffic Impacts
Page last updated: Aug. 14, 2026
Schedule: June 22 to Aug. 28, 2026
Anticipated work scheduled: Crews will:
- Install curb and gutter
- Place signs and begin restoration at the County YY intersection
Traffic impacts (the next 10 days):
- County YY intersection east of WIS 73 will be closed to traffic with no posted detour.
- County YY intersection western leg will be open with flaggers