WIS 73, White River Bridge to WIS 21

Waushara and Marquette Counties

Schedule and Traffic Impacts

Page last updated: July 2, 2026

Schedule: June 22 to Aug. 28, 2026

Anticipated work scheduled: Crews will:

  • Remove the culvert pipe at the Cottonville Road intersection
  • Patch asphalt pavement, concrete curb and gutter, and concrete sidewalk work in the village of Neshkoro

Traffic impacts (the next 10 days): 

  • Motorists will encounter single-lane closures with flaggers
  • NOTE: The County YY work and associated road closures on County YY previously planned to start on Monday, June 29 has been delayed due to utility conflicts discovered. The current plan is to delay some or all of that work until early August.