Schedule and Traffic Impact
Page last updated: July 24, 2026
Schedule: April 27 to Aug. 28, 2026
Anticipated work scheduled: Crews will:
- Continue grading for truck aprons in roundabout
- Continue placing material behind curb and gutter for sidewalks around roundabout
- Place concrete sidewalk and pedestrian curb ramps throughout roundabout
- Grade WIS 80 reconstruct area between 3rd Ave and Jonathan Street
- Grade WIS 73 culvert patch east of roundabout
Traffic impacts (the next 10 days):
- WIS 73/80 Intersection is closed. Traffic is detoured via County X to WIS 54 to WIS 73. County A is detoured County C.
- Single lane closures with flagging operations will be utilized at the reconstruct area on WIS 80 between 3rd Ave and Jonathan Street and at the culvert patch on WIS 73 east of the roundabout.
- Single lane closures with flagging operations will be utilized next week on WIS 80 through Pittsville.