WIS 73, WIS 80 Intersection and WIS 80

 Wood County

Schedule and Traffic Impact

Page last updated: June 26, 2026

Schedule: April 27 to Aug. 28, 2026

Anticipated work scheduled: Crews will:

  • Continue placing base material
  • Place topsoil

Traffic impacts (the next 10 days): 

  • WIS 73/80 Intersection is closed. Traffic is detoured via County X to WIS 54 to WIS 73. County A is detoured County C.
  • WIS 80 shoulder closures will be unutilized to direct pedestrians around the curb ramp work.
  • Roadway will have 11-foot width restriction.
  • Periodic flagging operations will occur when operations impact the travel lanes.
  • Curb ramp construction will be staged so that pedestrian access will be maintained at all times.