Schedule and Traffic Impact
Page last updated: May 1, 2026
Schedule: April 27 to Aug. 28, 2026
Anticipated work scheduled: Crews will:
- Begin removal of curb ramps
- Begin sawing asphalt and concrete
- Begin curb ramp construction.
Traffic impacts (the next 10 days):
- Roadway will have 11-foot width restriction.
- Single-lane closures with flaggers.
- Pedestrian detours for curb ramp work.
- Curb ramp construction will be staged so that pedestrian access will be maintained at all times.