Schedule and Traffic Impacts
Page last updated: July 2, 2026
Schedule: June 22 to Oct. 30, 2026
Anticipated work scheduled: Crews will:
- Pulverize pavement at culvert replacement locations
- Replace culvert pipes
- Grade at culvert replacement locations
- Perform restoration
- Patch culverts
Traffic impacts (the next 10 days):
- WIS 47 will be closed to thru traffic from County VV (west) to the Langlade County Line for culvert replacement operations. Traffic will be detoured via US 45 and WIS 29. Access by local traffic and emergency services will be maintained throughout the closure. The closure is anticipated to continue until mid-August.