WIS 55, WIS 47 to the Langlade County

 Menominee County

Schedule and Traffic Impacts

Page last updated: Aug. 29, 2025

Schedule: Sept. 2 to Sept. 22, 2025

Anticipated work scheduled: Crews will:

  • Install traffic control, erosion control and project staking.

Traffic impacts (the next 10 days):

  • WIS 55 from WIS 47 to the Langlade County line will be close to through traffic and detoured using WIS 22, WIS 32 and WIS 64 from Sept. 2 through Sept. 22.
  • For local traffic, WIS 55 will be reduced to one lane using flagging operations during daylight hours.