Schedule and Traffic Impacts
Page last updated: May 22, 2026
Schedule: April 14 to Aug. 31, 2026
Anticipated work scheduled: Crews will:
- Mill the asphalt shoulders, intersection crossings and median areas.
- Begin paving asphalt median areas, intersection crossings and shoulders.
Traffic impacts (the next 10 days):
- The median lanes in the eastbound and westbound directions on WIS 54 are closed to traffic from 26th Street North in Wisconsin Rapids to Bus 51/Post Road in Plover. The lane closures will be removed by noon on Friday, May 22 for the Memorial Day holiday weekend
- The median lane closures will be put back in place beginning May 26 at 6am