Schedule and Traffic Impacts
Page last updated: Aug. 14, 2026
Schedule: April 14 to Aug. 31, 2026
Anticipated work scheduled: Crews will:
- Continue sawing the concrete and asphalt as needed for the inlet adjustments and concrete pavement repair areas
- Continue removals and concrete work for the pavement repairs along the outside lane in the eastbound direction
- Begin removals and concrete work for the inlet adjustments along the outside curb and gutter
- Begin staking for curb ramps
Traffic impacts (the next 10 days):
- The outside lane in the eastbound and westbound directions WIS 54 will be closed to traffic from 26th Street North in Wisconsin Rapids to Bus 51/Post Road in Plover.
- Short term intersection turning movement closures as work requires.