WIS 47, Outagamie County Line to WIS 29

Shawano County

Schedule and Traffic Impact

Page last updated: May 17, 2024

Schedule: April 10 to July 2024

Anticipated work scheduled: 

  • Crews will be on site paving the highway from Wildlife Road to the north project limits
  • Crews will be on site cutting centerline rumble strips, along with placing shoulder gravel and painting pavement markings at various spots throughout the project

Traffic impacts:

  • Single-lane closures with flagging operations at various locations throughout the project for paving operations