Schedule and Traffic Impacts
Page last updated: May 1, 2026
Schedule: March 30 to Nov. 5, 2026
Anticipated work scheduled: Crews will:
- Begin removing the existing concrete pavement and grading for new concrete pavement on the westbound lane between County J on the western end of the project to Old 29 Road
- Seal the joint between the concrete pavement and new asphalt shoulders on the inside lanes and place new gravel shoulders
- Mill and pave the asphalt on the inside shoulders and crossovers
- Install temporary erosion control as needed
Traffic impacts (the next 10 days):
- The inside lanes are closed
- WIS 29 traffic will be relocated to the eastbound WIS 29 lanes using temporary crossovers. Motorists will encounter two-way traffic on the eastbound lanes of WIS 29 from County J on the western end of the project to Old 29 Road.