WIS 29, County J to County M, Eastbound

Shawano County

Schedule and Traffic Impacts

Page last updated: May 1, 2026

Schedule: March 30 to Nov. 5, 2026

Anticipated work scheduled: Crews will:

  • Begin removing the existing concrete pavement and grading for new concrete pavement on the westbound lane between County J on the western end of the project to Old 29 Road
  • Seal the joint between the concrete pavement and new asphalt shoulders on the inside lanes and place new gravel shoulders
  • Mill and pave the asphalt on the inside shoulders and crossovers
  • Install temporary erosion control as needed

Traffic impacts (the next 10 days): 

  • The inside lanes are closed
  • WIS 29 traffic will be relocated to the eastbound WIS 29 lanes using temporary crossovers. Motorists will encounter two-way traffic on the eastbound lanes of WIS 29 from County J on the western end of the project to Old 29 Road.