Schedule and Traffic Impacts
Page last updated: May 1, 2026
Schedule: April 13 to Oct. 20, 2026
Anticipated work scheduled: Crews will:
- Continue replacing concrete pavement
- Pave asphalt shoulders and place shoulder material on WIS 22 and WIS 117/47 ramps
- Begin paving shoulders on WIS 29
Traffic impacts (the next 10 days):
- WIS 29 will continue to have the inside lanes closed and WIS 29 eastbound to WIS 22 on and off ramps will remain closed.
- WIS 47/117 will remain closed with an anticipated open to traffic on May 8, 2026