Schedule and Traffic Impacts
Page last updated: June 19, 2026
Schedule: April 13 to Oct. 20, 2026
Anticipated work scheduled: Crews will:
- Complete the new asphalt shoulders on WIS 117/47 ramps and place new gravel shoulders
- Grind concrete patches for smoothness
- Mill and pave new outside shoulders on the portion of WIS 29 eastbound that had the new concrete placed.
Traffic impacts (the next 10 days):
- Westbound and Eastbound traffic is moved to the inside lanes
- Westbound traffic will have WIS 117/47 off and on ramps closed until June 26.