WIS 29, WIS 97 to Purple Martin Lane

Marathon County

Schedule and Traffic Impacts

Page last updated: July 2, 2026

Schedule: April 6 to Nov. 13, 2026

Anticipated work scheduled: Crews will:

  • Continue concrete pavement removals and grading
  • Place base materials
  • Trim base for concrete pavement
  • Pour concrete pavement on WIS 97, WIS 97 interchange ramp and WIS 29 westbound

Traffic impacts (the next 10 days): 

  • WIS 29 eastbound and westbound lane closures.
  • WIS 97 interchange will be closed through July 16, 2026.