WIS 22, WIS 54 and County B

Waupaca County

Schedule and Traffic Impacts

Page last updated: July 2, 2026

Schedule: June 11 to August 2026

Anticipated work scheduled: Crews will:

  • Continue to install cross culvert pipes from County BB to the north
  • Complete landscaping and restoration at the completed culvert pipes
  • Place asphalt surface at the completed culvert locations

Traffic impacts (the next 10 days): 

  • WIS 22 will be reduced to one lane during daytime operations from WIS 54/WIS 22 intersection to County B.