Schedule: June 11 to August 2026
Anticipated work scheduled: Crews will:
- Continue to install cross culvert pipes from County BB to the north
- Complete landscaping and restoration at the completed culvert pipes
- Place asphalt surface at the completed culvert locations
Traffic impacts (the next 10 days):
- WIS 22 will be reduced to one lane during daytime operations from WIS 54/WIS 22 intersection to County B.