WIS 22, WIS 54 and County B

Waupaca County

Schedule and Traffic Impacts

Page last updated: June 12, 2026

Schedule: June 11 to August 2026

Anticipated work scheduled: Crews will:

  • Begin construction staking for culverts
  • Begin sawing pavement for culvert pipe replacements
  • Install erosion control devices
  • Begin culvert pipe replacements

Traffic impacts (the next 10 days): 

  • WIS 22 will be reduced to one lane during daytime operations from WIS 54/WIS 22 intersection County B.