Schedule
Construction begins: April 2026
Anticipated completion: 2026
Traffic impacts
- The changing temporary configurations of STH 19 will continue into the early fall season.
- The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.
Project update
STH 19 Traffic Update:
- The Division Street intersection is currently open to all traffic movements. The center portion of the intersection was reopened yesterday.
IMPORTANT TRAFFIC UPDATE – FULL NIGHTTIME CLOSURE OF STH 19 NEXT WEEK (STH 113 ROUNDABOUT TO RIVER ROAD ROUNDABOUT)
- STH 19 WILL BE CLOSED FOR CROSS CULVERT REPLACEMENTS FOR 8 NIGHTS MINIMUM NIGHTLY FROM (7:30 PM UNTIL 6:00 AM).
– CLOSURES ARE SCHEDULED FOR THE NIGHTS OF MONDAY 8/24 THROUGH FRIDAY 8/28.
– CLOSURES WILL RESUME AFTER THE WEEKEND ON MONDAY 8/31 THROUGH WEDNESDAY 9/2 (WEATHER DEPENDENT).
- THIS WILL BE A FULL CLOSURE FOR ALL TRAFFIC (INCLUDING EMS). THERE WILL BE NO SIGNED DETOUR.
- THE CLOSURES WILL TAKE PLACE BETWEEN THE RIVER ROAD ROUNDABOUT AND THE STH 113 ROUNDABOUT.
- – BOTH ROUNDABOUTS WILL BE FUNCTIONAL IN THE NORTH/SOUTH DIRECTIONS, INCLUDING TRAVELING WESTBOUND FROM 113 AND EASTBOUND FROM RIVER ROAD.
- MOTORISTS WILL HAVE TO USE ALTERNATIVE ROUTES.
Construction Activities This Week:
- The curb and gutter crew finished pouring the median curb and gutter from Division to Raemisch.
- Once the median curb was cured, asphalt crews were in at night to finish the binder pavement from Raemisch, west through the Division intersection
- Traffic control crews reopened all lanes of the Division intersection following paving.
- Electrical crews finished all the traffic signal installations at Raemisch/Schumacher. The new signals are tentatively scheduled to be operational on September 9th.
- The grading crew worked to complete all excavation and stone placement at the new Hogan Road turn lanes.
- The storm sewer crew completed the installation of the new storm sewer system at the Hogan Road turn lanes.
Construction Activities for the week of August 24th:
- The storm sewer crew will work nightly to replace 5 culvert crossings between the STH 113 and the River Road roundabouts.
- Nightly milling and paving will start east of Raemisch and move east until complete for the foreseeable future.
- The concrete crew will pour all the new curb and gutter for the new Hogan Road turn lanes.
- The concrete crew will also pour the concrete sidewalk in the new median island (Division to Raemisch).