WIS 19 (Division Street to River Road)

Waunakee, Dane County

Schedule

Construction begins: April 2026

Anticipated completion: 2026

 

Traffic impacts

  • The changing temporary configurations of STH 19 will continue into the early fall season.
  • The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.

 

Project update

Traffic Update:

  • The north half of Division Street was reopened yesterday, Wednesday (7/8/2026).
  • Following the reopening of Division Street; Bruenig Blvd., Schumacher Rd., and Hogan Rd. were closed for reconstruction.

– Bruenig Blvd., Schumacher Rd., and south Hogan Road will be closed for approximately 3 weeks. (Weather permitting)

  • The changing temporary configurations of STH 19 will continue into the early fall season.
  • The temporary lanes have a maximum width of 11 feet, so wide loads cannot be accommodated.

Construction Activities This Week:

– The concrete sidewalks at Division Street were complete late last week. Topsoil followed this week and restoration is scheduled for today.

– Asphalt crews paved north Division Street and STH 19 at Division.

                – Traffic control and pavement marking crews were on site yesterday to reopen and reconfigure the Division Street intersection.

                – The excavation crew moved from the north side of Hogan Road to the south side and started pavement and curb removals.

Construction Activities for the week of July 13th:

  • Grading crews will continue to remove pavement and cut subgrade at Bruenig, Schumacher, and south Hogan Road.
  • Once removals are complete, crews will place the base aggregate at all three locations.
  • Toward the end of next week, crews will start placing the storm sewer system for south Hogan Road.