Schedule
Construction begins: April 2026
Anticipated completion: 2026
Traffic impacts
- The changing temporary configurations of STH 19 will continue into the early fall season.
- The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.
Project update
STH 19 Traffic Update: IMPORTANT UPDATES FOR NEXT WEEK
- Bruenig Boulevard, Schumacher Road, and Hogan Road south are scheduled to reopen next Thursday – 8/6/2026. (Weather permitting)
- Stage 3A will begin next Thursday. Stage 3A will construct the median of STH 19 from Schumacher Road through Division Street.
– This operation will require the closure of the middle of the Division Street intersection. STH 19 will be open (east/west) through Division, but you will not be able to travel (north/south) through the Division Intersection.
– The Division Street intersection construction will take approximately 2 to 3 weeks to complete.
- The changing temporary configurations of STH 19 will continue into the early fall season.
- The temporary lanes have a maximum width of 11 feet, so wide loads cannot be accommodated.
- The current westbound bi-directional traffic pattern will be shifted onto the new westbound pavement next Thursday (8/6/2026).
Construction Activities This Week:
- The concrete crew will finish the placement of the new curb and gutter on both sides of Hogan Road today.
– The concrete crew poured the north half of the median island from Schumacher Road to Division Street yesterday.
- The grading crew finish graded aggregate at Hogan Road, and on STH 19 from Bruenig Boulevard moving east through the Schumacher Road intersection.
- Electrical crews placed all the permanent traffic signal bases and pull boxes at the Schumacher / Raemisch intersection.
– The electrical crew all bored the necessary future conduits under STH 19 at Hogan Road.
– Stage 3A will take approximately 2 to 3 weeks to complete the middle section of STH 19 at Hogan Road and from Schumacher to Division.
Construction Activities for the week of August 3rd:
- Grading crews will fine grade the aggregate for pavement at Schumacher Road and Hogan Road Monday through Tuesday.
- The asphalt crews will be back on Wednesday to pave the north half of STH 19 from Division, east to the Schumacher farm. Hogan Road will also be paved.
- Traffic control crews and temporary paint crews will be on site Thursday to prepare for the stage 3A traffic switch.