Schedule
Construction begins: April 2026
Anticipated completion: 2026
Traffic impacts
- The changing temporary configurations of STH 19 will continue into the early fall season.
- The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.
Project update
– WIS 19 will be closed between WIS 113 and River Road October 10 and 11 for high friction surface treatment
– NIGHTWORK WILL CONTINUE TONIGHT (9/25) ON STH 19 FROM THE STH 113 ROUNDABOUT TO THE RIVER ROAD ROUNDABOUT
- THE WORK WILL BE COMPLETED UNDER A SINGLE LANE FLAGGING OPERATION.
- IF THERE ARE BACKUPS, MOTORISTS ARE ENCOURAGED TO USE ALTERNATIVE ROUTES.
Construction Activities This Week:
- The asphalt paving crew finished the final lift of asphalt from STH 113 to River Road in the eastbound lane.
- The concrete crew continued pouring the median sidewalk for the Hogan Road turn lanes.
- The sign crew started the placement of the permanent traffic signs.
- The pavement marking crew started the placement of the permanent pavement markings.
- The rumble strip crew finished all the project rumble strips last night.
Construction Activities for the week of September 28th:
- The pavement marking crew will finish all pavement markings by Monday of next week. (Weather permitting)
- Concrete crews will finish pouring the sidewalk for the Hogan Road median turn lanes.
- The shouldering crew will finish all their work by Monday of next week.
- The STH 19 reconstruction project will be substantially complete next week. Only punch list items will remain.