Schedule
Construction begins: April 2026
Anticipated completion: 2026
Traffic impacts
STH 19 Traffic Update:
- The traffic switch to the north side of STH 19 will be in place for the foreseeable future.
- The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.
- Marshall Road is open.
- The south half of Division Street is currently closed for construction and is scheduled to be reopened before Memorial Day (weather permitting).
- Nord Drive is open to all traffic and will not be impacted by construction.
Construction Activities This Week:
- Storm sewer crews were on site this week installing the storm water system for the south half of Division Street.
- The crew successfully closed STH 19 last night and placed three storm sewer lines across STH 19. The road was reopened at 6:00 AM.
- A bridge crew was on site and made repairs the Six Mile Creek box culvert.
- The electricians were on site this morning to place the conduits for the new traffic signals at Division Street.
Upcoming Construction Activities for the week of May 11th:
- Concrete crews will be in next week to pour the new curb and gutter for the south half of Division Street.
- The electricians will be back to finish the conduit and pull boxes for the intersection.
- Once the electricians are done, the new sidewalk will be poured for South Division Street.