Schedule
Construction begins: April 2026
Anticipated completion: 2026
Traffic impacts
- The changing temporary configurations of STH 19 will continue into the early fall season.
- The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.
- Raemisch Road (South of STH 19) is closed for reconstruction for the next 2 to 3 weeks.
- The South half Division Street is reopened and has a new traffic pattern with the north bound right lane as a right turn only to handle the new traffic volumes with Raemisch Road closed.
- Nord Drive is open to all traffic and will not be impacted by construction.
- Raemisch Road will only be closed at the intersection. You will have full access to all businesses and Culvers from Nord Drive.
- Eastbound STH 19 traffic was shifted to the north side of the highway at Raemisch Road.
Construction Activities This Week:
- South Division Street and STH 19 construction was finished this week. The new asphalt pavement was placed.
- Division Street was reopened, Raemisch Road was closed and traffic was shifted on STH 19 to accommodate the construction.
- Pavement marking crews were out to stripe the new configuration of STH 19 and Division Street.
Construction Activities for the week of May 25th:
- The contractor will begin the excavation of STH 19 and the Raemisch Road intersection.
- The new storm sewer culvert will be installed under Raemisch Road.
- Once complete new aggregate base course will be placed ahead of new curb and gutter.