WIS 19 (Division Street to River Road)

Waunakee, Dane County

Schedule

Construction begins: April 2026

Anticipated completion: 2026

 

Traffic impacts

STH 19 Traffic Update:

  • The traffic switch to the north side of STH 19 will be in place for the foreseeable future.
  • The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.
  • Marshall Road is open.
  • The south half of Division Street is currently closed for construction and is scheduled to be reopened before Memorial Day (weather permitting).
  • Nord Drive is open to all traffic and will not be impacted by construction.

Construction Activities This Week:

  • Storm sewer crews were on site this week installing the storm water system for the south half of Division Street.
  • The crew successfully closed STH 19 last night and placed three storm sewer lines across STH 19. The road was reopened at 6:00 AM.
  • A bridge crew was on site and made repairs the Six Mile Creek box culvert.
  • The electricians were on site this morning to place the conduits for the new traffic signals at Division Street.

Upcoming Construction Activities for the week of May 11th:

  • Concrete crews will be in next week to pour the new curb and gutter for the south half of Division Street.
  • The electricians will be back to finish the conduit and pull boxes for the intersection.
  • Once the electricians are done, the new sidewalk will be poured for South Division Street.