WIS 19 (Division Street to River Road)

Waunakee, Dane County

Schedule

Construction begins: April 2026

Anticipated completion: 2026

 

Traffic impacts

  • The changing temporary configurations of STH 19 will continue into the early fall season.
  • The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.

 

Project update

Closures will be tonight 8/28, Monday 8/31, Tuesday 9/1 and Wednesday 9/2. (NO WEEKEND CLOSURES)

FULL NIGHTTIME CLOSURES OF STH 19 TONIGHT, AND MONDAY THROUGH WEDNESDAY (9/2) OF NEXT WEEK (STH 113 ROUNDABOUT TO RIVER ROAD ROUNDABOUT)

  • STH 19 WILL BE CLOSED FOR CROSS CULVERT REPLACEMENTS THROUGH NEXT WEDNESDAY – (NIGHTLY FROM (7:30 PM UNTIL 6:00 AM).

– CLOSURES ARE WEATHER DEPENDENT AND SUBJECT TO CHANGE.

  • THESE WILL BE A FULL CLOSURES FOR ALL TRAFFIC (INCLUDING EMS). THERE WILL BE NO SIGNED DETOUR.
  • THE CLOSURES WILL TAKE PLACE BETWEEN THE RIVER ROAD ROUNDABOUT AND THE STH 113 ROUNDABOUT.
  • – BOTH ROUNDABOUTS WILL BE FUNCTIONAL IN THE NORTH/SOUTH DIRECTIONS, INCLUDING TRAVELING WESTBOUND FROM 113 AND EASTBOUND FROM RIVER ROAD.
  • MOTORISTS WILL HAVE TO USE ALTERNATIVE ROUTES.

Construction Activities This Week:

  • The curb and gutter crew finished pouring the curb and gutter for the new Hogan Road turn lanes.
  • The concrete crews also poured the sidewalk for the median island from Division to Raemisch.
  • The existing pavement was milled and repaved between Raemisch and STH 113.
  • Culvert replacements started this week nightly between STH 113 and River Road. These will continue through next Wednesday night.

Construction Activities for the week of August 31st:

  • The storm sewer crew will continue to work nightly to replace the 5 culvert crossings between the STH 113 and the River Road roundabouts.
  • Nightly milling and paving will start tonight east of STH 113 and move east until complete for the foreseeable future.