Schedule
Construction begins: April 2026
Anticipated completion: 2026
Traffic impacts
- The changing temporary configurations of STH 19 will continue into the early fall season.
- The temporary lanes have a maximum width of 11 feet, so no wide loads can be accommodated.
Project update
- Division Street was closed on the north side of STH 19 for reconstruction.
- Weather permitting, the plan is to reopen Division Street before the 4th of July.
- Raemisch Road was reopened into its new temporary configuration. (See attached photo)
- Traffic backups are common; the signal timing has been adjusted.
- Motorists are encouraged to use alternative routes (Hogan Road, Marshall Drive or Division Street)
- The changing temporary configurations of STH 19 will continue into the early fall season.
- The temporary lanes have a maximum width of 11 feet, so wide loads cannot be accommodated.
- Nord Drive is open to all traffic and will not be impacted by construction.
Construction Activities This Week:
- Division Street is closed on the north side of the STH 19 intersection. (See attached photos)
- Pavement removals have been completed and all base aggregate has been placed.
- Crews will begin to install the Division Street storm sewer system tomorrow.
Construction Activities for the week of June 22nd:
- Crews will finish the storm sewer on north Division Street next week.
- Once all storm sewer is complete, the electricians will install the necessary traffic signal conduits.
- Concrete crews will mobilize to place the curb and gutter by the end of next week. (Weather permitting)