Schedule and Traffic Impacts
Page last updated: June 19, 2026
Schedule: May 18 to July 24, 2026
Anticipated work scheduled: Crews will:
- Install deck rebar
- Pour bridge deck
- Begin 7-day curing of deck
Traffic Impacts:
- WIS 17 will be detoured onto adjacent County G to bypass the project site for bridge construction. Traffic is anticipated to stay in this detoured configuration through much of the month of July.