Schedule and Traffic Impacts
Page last updated: May 29, 2026
Schedule: April 13, 2026 to November 2026
Anticipated work scheduled: Crews will:
- Continue culvert pipe installation
- Continue grading
Traffic impacts (the next 10 days):
- WIS 13 will be closed to through traffic from 2nd Street North to County P. Traffic will be detoured via WIS 66, I-39, US 10
- Cross drain construction will begin. WIS 13 will have approximately three days of hard closures at the individual cross drain locations. Contractor will work north to south. First culvert will be just north of Lone Elm Road tentatively starting early in June.