WIS 13, 2nd Street North to County P

Wood County

Schedule and Traffic Impacts

Page last updated: June 19, 2026

Schedule: April 13, 2026 to November 2026

Anticipated work scheduled: Crews will:

  • Continue grading operations
  • Continue driveway culvert pipe/cross drain installations

Traffic impacts (the next 10 days): 

  • WIS 13 will be closed to through traffic from 2nd Street North to County P. Traffic will be detoured via WIS 66, I-39, US 10
  • Cross drain construction will begin. WIS 13 will have approximately three days of hard closures at the individual cross drain locations. Contractor will work north to south. The second culvert will be just south of Thilo Road.