Schedule and Traffic Impacts
Page last updated: Sept. 4, 2026
Schedule: April 13, 2026, to November 2026
Anticipated work scheduled: Crews will:
- Begin paving asphalt
Traffic impacts (the next 10 days):
- WIS 13 will be closed to thru traffic from 2nd Street North to County P. Traffic will be detoured via WIS 66, I-39, and US 10.
- Access within the project will be down to one lane during milling and pulverizing operations. Property owners should expect short-term blocking of their driveways during the milling and relay operations.