WIS 13 Bayfield

_

Schedule

 

Both projects will be conducted under traffic with the use of flagging operations and single lane closures. WIS 13 will remain open to two-way traffic during night time and weekend hours.

Culvert construction began in April 2017 and was completed in July 2017.

Work for resurfacing, sign and beamgaurd replacement began on July 10 and is scheduled for completion in October 2017.