WIS 130 bridge over Wisconsin River

Lone Rock, Iowa/Richland/Sauk counties

Schedule

On Tuesday, June 18th WisDOT Bridge Inspectors are scheduled to perform standard annual inspection on the existing south bridge. Traffic across the bridge will be flagged to a single lane most of the day starting at 8:00AM.

RIVER NAVIGATION UPDATE:

  • South Channel will remain closed for the next few months
  • North Channel will remain open and is currently wide open with the rock causeway removed from the channel
  • Current Boating Guide attached for reference

NORTH BRIDGE UPDATE:

  • Final touch-up and staining completed this week.
  • Seal the deck to take place next week.

SOUTH BRIDGE UPDATE:

  •  Installation of deck formwork and rebar.
  • Two concrete deck pours are planned for late June / early July.

Future

Spring/Summer 2024:

  • Bridge substructures and superstructures, WIS 130 roadway

Fall 2024:

  • Traffic shifts to new WIS 130 alignment on new bridges and roadway, start causeway access for removing old bridges

Winter/Spring/Summer 2025:

  • Remove old bridges and old WIS 130 roadway core, restoration, Brace Memorial Park interpretive panels