Anticipated work schedule for the week of 5/18/16 – 5/25/16:

  • Continue forming edge of deck and pedestal bases in span 4 & 5
  • Continue forming pier 3 & 4 maskwalls
  • Continue placing reinforcing steel for pier 2 & 3 diaphragms
  • Continue placing deck reinforcing steel in spans 1, 2, & 3
  • Placing pier 1 & 2 maskwall reinforcing steel