Construction update
Anticipated work schedule for the week of 5/18/16 – 5/25/16:
- Continue forming edge of deck and pedestal bases in span 4 & 5
- Continue forming pier 3 & 4 maskwalls
- Continue placing reinforcing steel for pier 2 & 3 diaphragms
- Continue placing deck reinforcing steel in spans 1, 2, & 3
- Placing pier 1 & 2 maskwall reinforcing steel