Schedule and Traffic Impacts
Page last updated: April 24, 2026
Schedule: April 20 to September 2026
Anticipated work scheduled: Crews will:
- Begin roundabout construction at County G and WIS 17 South
- Begin construction of temporary road to maintain access from WIS 17 South to US 8
Traffic impacts (the next 10 days):
- During construction, US 8 will be closed during construction and detoured onto WIS 17 North, Lincoln Street, South Courtney Street, Pelham Street, Arbutus Street and Kemp Street.