Schedule: April 20 to September 2026
Anticipated work scheduled: Crews will:
- Remove existing asphalt and concrete pavement
- Install new storm sewer
- Install electrical components for the new street lighting
Traffic impacts (the next 10 days):
- During construction, US 8 will be closed during construction and detoured onto WIS 17 North, Lincoln Street, South Courtney Street, Pelham Street, Arbutus Street and Kemp Street.