Schedule
Construction begins: August 18, 2025
Anticipated completion: late November/early December 2026
Traffic impacts
Lane Closures and Detours:
- Lane closures will be required on various lanes of US 61 for base patching and milling operations. Temporary Regulatory Speed Limit Reductions will be used in the active work areas. Lane closures will utilize a Digital Speed Reduction System (DSRS) that will notify travelling public of the current speed limit in the work areas of the project. Lane closures will remain in place day, and night as work operation require their use. Please follow and obey the work zone speed limit.
- Lane closures will be required on WIS 11 for pavement removal, grading, and paving operations. A single-lane automated traffic signal system will be in place at the far east project limit on WIS 11 for a portion of the WIS 11 work area due to restricted working width in that area. We ask that all motorists stay alert in this area for slowed or stopped traffic.
- Ramp closures will be required to repair the ramps at the WIS 11 and US 61 interchange, the Badger Road interchange with US 61, the Eagle Point Road Interchange with US 61, and the ramps at the split diamond interchange at Kieler. These ramp closures will occur at various times throughout the project. All ramp closures will be accompanied by a corresponding signed detour route. Please pay close attention revised routing at detour signage in the project vicinity.
Update for 11/9 to 11/15:
USH 61
Work:
- Crews will continue asphalt surface layer paving between Eagle Point Road and the STH 11 overpass in the outside travel lanes and ramps.
- Crews will continue shouldering the outside shoulders from Eagle Point Road to the STH 11 overpass.
- Temporary barrier wall will be removed from the Kieler interchange structures early Tuesday morning November 10, 2026.
- Guardrail will be installed at the Kieler interchange structures on the outside shoulders late in the week.
- All activities are weather dependent which can impact progress.
Traffic:
- Lane closures will continue along USH 61 NB and SB from the Dickeyville exit and entrance ramps to the STH 11 overpass.
- Traffic will remain in the median travel lane from the Dickeyville interchange to the STH 11 overpass in both NB and SB directions.
- Speed Limit 55 mph during work operations daily. Please obey posted speeds.
SOUTHBOUND KIELER INTERCHANGE (EXIT AND ENTRANCE RAMPS)
Work:
- Ramps are currently open.
- All activities are weather dependent which can impact progress.
Traffic:
- Ramps are currently open.
- Detour not required.
NORTHBOUND KIELER INTERCHANGE (EXIT AND ENTRANCE RAMPS)
Work:
- Ramps are currently open.
- All activities are weather dependent which can impact progress.
Traffic:
- Ramps are currently open.
- Follow posted Detours.
SOUTHBOUND EAGLE POINT (EXIT AND ENTRANCE RAMPS)
Work:
- Ramps are currently open.
- Crews anticipate milling, asphalt paving, and gravel shouldering the ramp shoulders on 11/16 to 11/17 (now anticipated due to current weather).
- All activities are weather dependent which can impact progress.
Traffic:
- Ramps are currently open.
- Ramps will be closed for a limited duration to accommodate final asphalt surfacing and gravel shouldering on 11/16 and 11/17.
- Follow posted Detours.
NORTHBOUND EAGLE POINT (ENTRANCE RAMP)
Work:
- Ramp is currently open.
- All activities are weather dependent which can impact progress.
Traffic:
- Ramp open to traffic currently.
- Detour not required.
NORTHBOUND STH 11 INTERCHANGE (ENTRANCE RAMP)
Work:
- Crews anticipate milling shoulders, asphalt paving, gravel shouldering, and guardrail removal and replacement on the ramp from 11/11 to 11/14 (now anticipated due to weather delays).
- All activities are weather dependent which can impact progress.
Traffic:
- Ramp will be closed to accommodate this construction.
- Follow the posted Detour.
BADGER ROAD INTERCHANGE:
Work:
- Crews completed final asphalt surfacing. Crews will also perform final shaping and grading of the shoulders.
- All activities are weather dependent which can impact progress.
Traffic:
- Badger Road will remain open to traffic (flagging work operations as necessary).
- The NB Badger Road Exit Ramp (Exit 2) will remain closed for repairs on Badger Road. Access to/from the Maryville Heights area will be via Exit 1, STH 11, to Badger Road. Access to /from points west and north of the Badger Road interchange bridge will be via Badger Road to Eagle Point Road to the SB entrance ramp to USH 61 SB.
- The SB Badger Road Entrance Ramp will remain closed for repairs on Badger Road. Traffic can follow Badger Road EB to STH 11 to access USH 61 or travel NB and utilize the SB entrance ramp at Eagle Point Road.
- Detour not required.
Next week: (11/16 to 11/22)
USH 61
Work:
- Crews will continue asphalt surface layer paving between Eagle Point Road and the STH 11 overpass in entrance and exit ramps.
- Crews will continue shouldering the outside shoulders from Eagle Point Road to the STH 11 overpass.
- Crews will install guardrail from Eagle Point Road to the STH 11 overpass in both travel directions late in the week.
- Crews will begin pavement marking and rumble strip grooving.
- All activities are weather dependent which can impact progress.
Traffic:
- Lane closures will continue along USH 61 NB and SB from the Dickeyville exit and entrance ramps to the STH 11 overpass.
- Traffic will remain in a single travel lane from the STH 11 overpass to the Dickeyville exit and entrance ramps in both NB and SB directions.
- Speed Limit 55 mph during work operations daily. Please obey posted speeds.
SOUTHBOUND KIELER INTERCHANGE (EXIT AND ENTRANCE RAMPS)
Work:
- Crews will place pavement markings and mill rumble strips.
- All activities are weather dependent which can impact progress.
Traffic:
- Anticipate closures of limited duration for pavement markings and rumble strip milling.
- Detour not required.
NORTHBOUND KIELER INTERCHANGE (EXIT AND ENTRANCE RAMPS)
Work:
- Crews will place pavement markings and mill rumble strips.
- All activities are weather dependent which can impact progress.
Traffic:
- Anticipate closures of limited duration for pavement markings and rumble strip milling.
- Follow posted Detours.
SOUTHBOUND EAGLE POINT (EXIT AND ENTRANCE RAMPS)
Work:
- Crews anticipate milling, asphalt paving, and gravel shouldering the ramp shoulders on 11/16 to 11/17 (now anticipated due to weather).
- All activities are weather dependent which can impact progress.
Traffic:
- Ramps will be closed for a limited duration to accommodate final asphalt surfacing and gravel shouldering.
- Follow posted Detours.
NORTHBOUND EAGLE POINT (ENTRANCE RAMP)
Work:
- No work anticipated, ramp currently open.
- All activities are weather dependent which can impact progress.
Traffic:
- Ramp open to traffic currently.
- Detour not required.
NORTHBOUND STH 11 INTERCHANGE (ENTRANCE RAMP)
Work:
- Crews anticipate milling shoulders, asphalt paving, gravel shouldering, and to complete guardrail placement on the ramp from 11/17 and 11/18 (now anticipated due to weather delays).
- All activities are weather dependent which can impact progress.
Traffic:
- Ramp will be closed for a limited duration to accommodate this construction.
- Follow the posted Detour.
BADGER ROAD INTERCHANGE:
Work:
- Crews anticipate installing guardrail on Badger Road.
- All activities are weather dependent which can impact progress.
Traffic:
- Badger Road will remain open to traffic (flagging work operations as necessary).
- The NB Badger Road Exit Ramp (Exit 2) will remain closed for repairs on Badger Road. Access to/from the Maryville Heights area will be via Exit 1, STH 11, to Badger Road. Access to /from points west and north of the Badger Road interchange bridge will be via Badger Road to Eagle Point Road to the SB entrance ramp to USH 61 SB.
- The SB Badger Road Entrance Ramp will remain closed for repairs on Badger Road. Traffic can follow Badger Road EB to STH 11 to access USH 61 or travel NB and utilize the SB entrance ramp at Eagle Point Road.
- Detour not required.