US 53, 40th Avenue to County B

Chippewa County 

Schedule

Construction in 2025 is scheduled to:

  • Start: March 10
  • Be completed: Late October

Work will be shut down over the winter and resume in spring 2026, with the entire project completed in late June 2026.