Schedule and Traffic Impacts
Page last updated: June 26, 2026
Schedule: April 6 to June 18, 2026, and Sept. 8 to Oct. 9, 2026
Anticipated work scheduled: Crews will:
- Finish placing concrete sidewalk
- Install topsoil, seed, erosion material and install asphalt in driveways and patches.
- Sweep the roadway and general clean up
Traffic impacts (the next 10 days):
- All traffic control is expected to be removed June 18 for the remainder of the summer. Work will resume on the project Sept. 8.