Schedule and Traffic Impacts
Page last updated: May 30, 2025
Schedule: April 24 to October, 2025 (no work between June 13 and Sept. 1)
Anticipated work scheduled: Crews will:
- Continue to remove curb and gutter, and sidewalk at various locations
- Place and grade gravel in the curb and sidewalk locations
- Start placing concrete curb and gutter and sidewalk at various locations
- Place topsoil and seed at various locations
Traffic impacts (the next 10 days): Northbound and southbound driving lanes are closed, will maintain one through lane of traffic in each direction.