Schedule and Traffic Impacts
Page last updated: May 9, 2025
Schedule: April 24 to October, 2025 (no work between June 13 and Sept. 1)
Anticipated work scheduled: Crews will:
- Continue replacing concrete curb, gutter and sidewalk at various locations
- Patch the asphalt along the curb and gutter with asphalt
- Restore the areas along the newly installed sidewalk with topsoil
Traffic impacts (the next 10 days): Motorists will encounter a closure of the northbound and south bound right lanes. One through lane of traffic will remain in each direction.