US 51, US 8 to Bearskin Bridge (County L)

Oneida County

Schedule and Traffic Impacts

Page last updated: April 17, 2026

Schedule: April 6 to June 19, 2026

Anticipated work scheduled: Crews will:

  • Continue concrete removal and replacement
  • Continue structure work

Traffic impacts (the next 10 days): 

  • US 51 will be closed to through traffic from US 8 to County L.
  • US 51 traffic will be detoured using US 8 and WIS 47. This detour will remain in place until May 15, 2026.