Schedule and Traffic Impacts
Page last updated: May 1, 2026
Schedule: April 6 to June 19, 2026
Anticipated work scheduled: Crews will:
- Continue concrete removal and replacement
- Begin replacing bridge approach slabs
- Continue structure work at various structures
- Mill asphalt surfaces
Traffic impacts (the next 10 days):
- US 51 will be closed to through traffic from US 8 to County L.
- US 51 traffic will be detoured using US 8 and WIS 47.
- This detour will remain in place until noon May 21, 2026. The road will be open for Memorial Day weekend