US 51 (Tower Road to Exchange Street)

Dane County

Schedule

Construction begins: April 1, 2026

Anticipated completion: November 13, 2026

 

Traffic impacts

US 51 will remain open to traffic with shoulder closures

 

Project update

Crews are continuing to make progress on the center of the roundabouts and are still hoping to wrap up the project by the end of next week. Please slow down and use caution when navigating the roundabouts. There will continue to be quite a bit of activity in the medians and outside shoulders in these areas over the next week. Below is this week’s update.

  • Remainder of this week: Crews will wrap up the remainder of the concrete placement, weather dependent. With morning showers the next couple days, crews are anticipating continuing to work once the rain stops. Electrical work will also continue, and pavement markings will start to be installed.
  • Weekend work: Crews may be in this Saturday working on finishing up placing topsoil.
  • Week of November 9th – The remainder of the signing and markings will be installed. Restoration should also be completed bringing an end to this segment of the reconstruction of USH 51.

Stage 4 Notes:

The roundabouts at Exchange St and Tower Rd are open and all turning movements are permitted. There will however be intermittent closures of left turns at both the Exchange St and Tower Rd roundabouts. These will be limited to be between the hours of 9 am to 3 pm. This is so that construction vehicles have access to construct the remaining halves of the roundabouts. Signing and drums will be in place when the movements are restricted.

There are currently minimal roadway markings. In order to finish the remaining items, lane shifts are expected to be frequent. Please slow down and pay attention to the traffic control devices directing traffic.

Adjacent Projects:

Work is continuing on the project to the north of Exchange St. That project in not tied to this project from Tower Road to Exchange St. If you are looking to get on the mailing list for the weekly updates on that project, please send an email to USH51Project@strand.com and request to be added to their mailing list.

They are anticipating closing USH 51 at the Yahara River Bridge around December 1st. 2026 to replace the bridge. They are anticipating reopening the bridge around early July 2027.

USH 51 south of Tower Rd is slated for construction in the spring of 2027. This project will close USH 51 from Tower Rd to the CTH B/AB roundabout. The CTH B/AB roundabout will remain open and operational during that project closure. There is no mailing list yet for this project and this project has not been advertised for construction yet. There is information on the project on WisDOT’s website: https://wisconsindot.gov/Pages/projects/by-region/sw/us51-danecounty/Rural.aspx#exhibits