Schedule
Weekly update
Construction begins: March 3, 2025
Anticipated completion: November 2025
Traffic impacts
Stage 1:
Location: install guardrail in median along northbound US 51.
Traffic:
- US 51 northbound median lane closed, US 51 SB median shoulder closure.
- This stage is currently scheduled to be completed in mid-March.
Stage 2a:
Location: US 51 southbound and southbound bridge over Taylor Road.
Traffic:
- US 51 on existing northbound.
- Taylor Road work will be closed.
- Sigglekow Road will remain open, but both northbound ramps and the southbound on-ramp at Sigglekow Road will be closed.
- The southbound off-ramp to eastbound Sigglekow Road will remain open through the entire stage.
- Stage 2a is currently scheduled to be completed in mid-April.
- See below for an exhibit showing traffic restrictions at Sigglekow Road during this stage.
Stage 2b:
Location: US 51 southbound, southbound bridge over Taylor Road and Sigglekow Road.
Traffic:
- US 51 on existing northbound.
- Taylor Road will be open through traffic.
- Sigglekow Road, as well as both northbound ramps and the southbound on-ramp at Sigglekow Road will be closed.
- The southbound off-ramp to eastbound Sigglekow Road will remain open through the entire stage.
- Stage 2b is currently scheduled between mid-April to August 2025.
- See below for an exhibit showing traffic restrictions at Sigglekow Road during this stage.
Stage 3:
Location: US 51 northbound.
Traffic:
- US 51 traffic on new southbound lanes.
- Siggelkow Road and Taylor Road open.
- Northbound Siggelkow Road interchange ramps will be closed.
Stage 4:
Location: US 51 median.
Traffic:
- US 51 northbound and southbound will be open with off-peak lane closures.
- Sigglekow Road and all ramps will be open.