Schedule
Construction begins: July 13, 2026
Anticipated completion: late fall 2026
Traffic impacts
Traffic on US 51 will be maintained in stages:
- Stage 1: One lane of traffic in each direction will be maintained on the outside lanes while work occurs on the inside lanes.
- Stage 2: Traffic will then shift to the inside lanes while work is completed on the outside lanes.
Additional impacts include:
- No left turns from Delavan Drive during construction
- Short-term closures and flagging operations at times
- Access to local properties will be maintained whenever possible
- Temporary interruptions to driveways or sidewalks may occur during active work; advance notice will be provided when access is affected
Weekly update
Current Construction Operations:
- Traffic was switched to the outside lanes to complete work on the inside lanes
- Guardrail was installed on the NB side
- Median Curb and Sidewalk form and pour concrete.
Upcoming Construction Operations:
- Crews will finish pouring the concrete for the curb and sidewalk in the median.
- Milling and Asphalt paving anticipated for late this week on the median lanes.
Traffic Updates:
- USH 51 Traffic –
- The NB and SB lanes are on the outside lanes in a single lane each direction.
- One lane in each direction will remain open on Center Ave.
- The intersection of Center Avenue and Delavan Drive will remain as a signalized intersection. All movements will be allowed through the intersection except to and from the west leg of W. Delavan Dr.
- Delavan Drive –
- The west leg of the intersection will remain closed to all traffic during construction.